Sun Fire 15K/12K Systems Site Planning Guide • June 2003
❏
Does the computer room environment meet the Sun Microsystems specifications
for temperature and humidity listed in
?
❏
Confirm there is sufficient unused cooling capacity supporting the computer
area to handle the increase in load from this system. Redundant capacity should
not be considered. See
.
❏
Verify the number of circuit breaker pole positions are available to connect the
systems properly.
❏
Determine the source of power for the proposed systems. Are the sources of
power consistent with the intended power connection configurations shown in
, or
?
❏
Is the computer room voltage between 200–240 VAC?
❏
Have sufficient power receptacles been ordered for the system cabinet and each
customer selected I/O expansion rack (
❏
Ensure the power receptacles are within 14 ft (427 cm cable length) of the system
cabinet and each customer selected I/O expansion rack location.
❏
Are the circuit breakers for the system cabinet and each customer selected I/O
expansion rack properly installed and labeled?
❏
Has the system location been established?
❏
Does the equipment floor layout meet the equipment maintenance access
requirements? See
Section 2.3, “Computer Room Layout” on page 2-6
❏
Confirm the equipment is positioned so that the minimum distance from the
discharge of a heat-rejecting device meets the suggestions in
.
❏
Are the floor cutouts for the system cabinet and each customer selected I/O
expansion rack in place?
❏
Are suggested perforated floor panels in place? See
Summary of Contents for Sun Fire 12K
Page 6: ...vi Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 8: ...viii Sun Fire 15K12K Systems Site Planning Guide June 2003...
Page 10: ...x Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 14: ...xiv Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 28: ...1 14 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 44: ...3 8 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 60: ...A 2 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 64: ...A 6 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 66: ...A 8 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 68: ...A 10 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 70: ...A 12 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 72: ...A 14 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 74: ...A 16 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 76: ...A 18 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 78: ...A 20 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 80: ...A 22 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 82: ...A 24 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 83: ...B 1 APPENDIX B Compliance Statements...
Page 84: ...B 2 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 96: ...B 14 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Page 100: ...Index 4 Sun Fire 15K 12K Site Planning Guide June 2003...