17 COMMISSIONING THE BOILER
17.1 First: flushing the boiler with water
After installation of the boiler the first step, before commissioning, is to flush the boiler and the whole heating
installation with fresh water to remove pollution, debris and other materials that might cause a blocking. This must
also be done with heating installations, where only the boiler is replaced.
Existing and new heating systems must be cleaned with a hydronic system cleaner; see chapter 7.14 "Flush the
system with fresh water. System cleaner must be drained and thoroughly flushed with clean water to remove any
residual cleaner, prior to installing a new boiler. NEVER leave a system cleaner for longer than recommended by
the manufacturer of the cleaner. Never put system cleaner inside the boilers heat exchanger.
17.2 Second: filling & venting the boiler and the system
After flushing the boiler and the installation the system can be filled with fresh water. Fill the boiler and the heating
system by using the appropriate filling valve. The water pressure of the system normally lies between 1,5 and 2,0
bar (21.8 and 40 psi) – see chapter 7.18 ‘Water pressure’
NOTICE: Use the following aspects to prevent corrosion of the central heating system:
•
Filling water: Do not use any additives for the water of the central heating system, except glycol. The pH value
of the water should be more than 5 (If this pH value is less, please contact the supplier).
•
Ensure that any used “plastic” pipes are oxygen diffusion-proof in accordance with DIN 4726/4729. If not,
make sure that the boiler circuit is separated from the heating circuit by a plate heat exchanger. This way no
oxygen that entered the heating system through these pipes can reach the boiler.
Check the total heating system for any leaks. This to prevent oxygen entering the system through these leaks.
The boiler has an automatic air vent situated inside the boiler. This vent is always open, and the venting outlet
goes via a plastic tube through the bottom to the outside. Shortly after putting the boiler into operation, check the
water pressure and add or remove some water to obtain the required pressure.
During the commissioning, make sure that no water can enter the boiler and make contact with the electrical parts.
17.3 Third: check the water flow
Before starting the boiler ensure the pump is installed and operating correctly and that there are no obstructions
or closed valves that could prevent water flow through the heat exchanger.
NOTICE: Always ensure the boiler pump is functioning correctly and that there is flow through the heat
exchanger after working on the boiler or system.
Summary of Contents for S-CBX 105
Page 2: ......
Page 40: ...40 9 10 Flue Terminal Positioning ...
Page 42: ...42 9 11 1 FIGURE 12 LINE G ...
Page 55: ...55 11 5 Ladder Logic Diagram ...
Page 56: ...56 11 6 Electrical schematics ...
Page 57: ...57 ...
Page 137: ......