Room Requirements
Space and Component Location Planning
3-5
Room Requirements
To ensure that the installation site provides a properly equipped, cooled, and sized
environment, make sure that the site:
Is a computer room
Provides clearances for air circulation, opening cabinet doors, removing cabinet
panels, and servicing the system from the front and rear.
Locate the front and rear of the system at least 2.5 feet (ft) (0.76 meters (m)) from
walls and other obstructions.
Maintains reasonable temperature and humidity levels and has a thermometer and
humidistat to monitor room temperature and humidity.
See
Chapter 2, “AC Power Planning”
for detailed information about HVAC planning
Appendix A, “System Specifications”
for detailed information on temperature
and humidity requirements.
Is as free as possible of airborne contamination (particulate and gaseous).
Optional U760 Eight-Port Serial
Synchronous PICMG 2.16
Adapter
Inside NIO enclosure
rackmounted in system cabinet
Place network connection
points within 4 feet of system
(length of adapter hydra
cables minus vertical runs)
Table 3-2. Location of V Series System Components
(Page 2 of 2)
Component
Location of Component
External Component
Location