Connecting External Components to the System
2-20
Stratus ftServer V 2302, V 4304, and V 6308 Hardware Installation Guide
(R003S)
Connecting the UPS
Perform the following tasks to connect each UPS unit to your ftServer module.
1. Assemble the UPS unit. Make sure that each UPS unit is properly assembled by
following the assembly and physical installation instructions described in the UPS
vendor’s documentation.
2. Connect the AC power cords to the UPS unit. For Chloride and APC UPS models
qualified by Stratus, the AC input cord must be hard wired to the UPS unit. See the
Stratus ftServer V 2302, V 4304, and V 6308 Systems: Site Planning Guide
(R624)
for a list of qualified UPS models.
W A R N I N G
!
Hard wiring the AC input and output cords to the UPS
unit must be performed by a qualified electrician in
compliance with local and national electrical code.
An electrician must supply and hard wire an appropriate AC input cord to each UPS
unit.
For UPS models not qualified by Stratus, you must work with the UPS vendor and
an electrician to properly connect the UPS units to the PDUs in the ftServer
module.
3. Use two customer-provided Category-5 Ethernet cables to connect the UPS units
to the U772 Ethernet switches (
a. Connect the Ethernet port on the A-side UPS unit to port 23 on U772 Ethernet
Switch A.
b. Connect the Ethernet port on the B-side UPS unit to port 23 on U772 Ethernet
Switch B.