IP Telephone Programming
xIPU and IPT Program Update
Strata CIX Programming Vol.1 12/09
8-33
IP T
e
le
phone
Pr
ogra
mming
xIPU and IPT Program Update
To start updating the xIPU or IPT firmware, the update firmware files must be stored on FTP Server (see
Appendix B – Software and Firmware Updates on page B-1
). You can update the xIPU using Network
eManager. You cannot update a BIPU-Q. If you need to update a BIPU-Q, return it to Toshiba.
Network eManager automatically disables the xIPU before any xIPU/IPT program update and preserves
the initial state of the xIPU (idle or disable) after program update is done.
The xIPU program update has two processing options: sequential and simultaneous. If the FTP server is a
CIX (SmartMedia) sequential processing must be used.
The IPT program update is performed sequentially only. A table sorted by xIPU shows a summary of the
IPT selection. You can select multiple IPTs. You can change the selection at any time before the update
process starts. The process flow is as follows:
•
The xIPU corresponding to the first group of IPTs is automatically disabled (if its current status is idle)
•
IPTs are updated one by one. Up to maximum 128 IPTs can be selected for one updating process.
•
xIPU is re-enabled (if its initial state was idle)
These steps are repeated automatically until the entire user selection is processed.
Both the xIPU and IPT update pages have an
Abort
and
Abort All
button. The
Abort
button is available
per item (xIPU, IPT), only when the current processing status allows the abort operation. Aborting the
update process is allowed only in two phases “Getting the update file” and “Resetting.”
The
Abort All
button is available when an update is in progress. You can click on
Abort All
to abort all
updates starting with the one currently processing. If abort operation is not allowed at the time, the
message “Please wait while system has a chance to abort…” appears. All program update processes will
be aborted when this is allowed by the CIX.
The synchronization between Network eManager and the CIX is not perfect during this process. Network
eManager sends a command, then checks for the completion of the command. If you click on
Abort
at the
end of the “Getting the update file” phase, Network eManager will abort in the next phase that abort is
allowed, which is resetting.
Summary of Contents for CIX 200
Page 42: ...Network eManager 2 4 Strata CIX Programming Vol 1 12 09 ...
Page 43: ...Network eManager Strata CIX Programming Vol 1 12 09 2 5 Network eManager ...
Page 44: ...Network eManager 2 6 Strata CIX Programming Vol 1 12 09 ...
Page 314: ...This page is intentionally left blank ...
Page 432: ...This page is intentionally left blank ...
Page 434: ...This page is intentionally left blank ...