Mounting instructions for multiplay equipment „ascendo robinia“
Item-No. 517510601
Foundation plan
Diagram 2b: Top view with dimension details of the foundations
450
850
400
3371
A
A
3652
706
1511
3645
4808
4027
1750
600
600
950
275
2880
1846
2909
1750
400
1100
500
1000
500
979
950
1750
561
2034
2005
A-A
6338
5373
OHNE SCHRIFTLICHE ZUSTIMMUNG DER KAISER GMBH DARF DIESE
TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT, NOCH DRITTEN MITGETEILT ODER
ZUGÄNGLICH GEMACHT WERDEN, NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VER-
WENDET WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.
Oberflächen nach
DIN ISO 1302
Reihe 2
Zul. Abweichung
DIN 2768 - mH
1
ascendo 2A
Benennung
Gepr.
Werkstoff
Blatt
Datum
Projekt
Gez.
Zuschnitt
Zeichnungsnummer
Rev
Änderung
Datum
1:50
A3
Gewicht
Name
Name
Fundamentplan
1028-00-00
1202.2
Maßstab
Mattheis
02.05.17
Gewerbegebiet Larsheck
56271 Kleinmaischeid
Deutschland
Beton
Concrete
Füllmaterial
Filling
Erde
Ground
Legende
4. After a setting period of 10-14 days, depending on weather condi-
tions and foundation size - clean the surface of the foundations and
start with the installation of the combination equipment.
5. Place the two towers as shown in Diagram 1, 2a and 2b at the
main foundations and do a rough aligning. Please take care that
the connections für the wobble bridge (shown in diagram 4) are
positioned face to face.
Note: Do not screw the base plates onto the foundations yet!
6. Hook in the wobble bridge as shown in diagram 4a and screw it
with the screws included in the delivery.
7.
Place the slide and the climbing slant at the shafts and fix it with
the screws and the adapter for the pipes which are included in the
delivery (diagram 4b).
8.
Connect the climbing bow and the two fireman‘s posts according to
diagram 4a at the adapters and screw it.
9. Align the whole play equipment once more at the foundation and
take care that every base plate is positioned in the center of the
foundation.
10. Drill holes into all foundations and screw the play equipment into
the foundations with the included heavy-duty dowels.