When working, the temporary mains power connection can be disconnected,
and the cable channels fastened using spacer bushings, screws and rings.
8.6 Cylinder bleeding
The cylinders are fitted with an SW10 nipple for bleeding air at the top. While
raising, turn the nipples once round to loosen them and wait until there is a
constant flow of oil without air bubbles. Then turn the nipples to the closed
position.
8.7 Testing
Once all the installation work has been done and the checks carried out, the lift
needs to be tested with a full load.
8.8 Load test
In order to carry out the static and dynamic tests on the Freedomlift as per DRT
circular no. 2005-04 dated 24-Mar-2005 perform:
• a static test of 60 minutes.
• a dynamic test of 15 minutes.
Perform the tests with a coefficient of 1.10.
Failure to follow these instructions could damage the lifting system and thereby
risk invalidating the warranty.
Summary of Contents for Freedomlift SK 2055
Page 108: ...Installation and Service Manual 108 SK 2055 2070 2090 14 2 Electrical diagram 3 x 230V ...
Page 109: ...Installation and Service Manual 109 SK 2055 2070 2090 14 3 Electrical diagram 3 x 400V ...
Page 113: ...Installation and Service Manual 113 SK 2055 2070 2090 14 6 Dimensions SK 2055 3 piece arms ...