background image

STPM-II-2

7/18

Pedestal mounted enclosure is not recommended for use with 

steam systems.

1.  Per the mechanical drawings, layout the pedestal brackets 

based on the enclosure lengths of the run. For enclosures 

2'-0" to 5'-0" lengths, two (2) brackets will be required. 

These brackets should start and end 6" to 12" in from each 

end of the enclosure. For enclosures 5'-6" to 8'-0" lengths, 

three (3) brackets will be required. The third bracket will be 

centered between the two outer brackets.

2.  Once the bracket locations along the run have been 

determined, secure them to the floor with the specified 

fasteners (by others). The rear vertical bracket leg should 

be a minimum of 2" from the wall. Depending on the flatness 

of the finished floor, it has to be determined which (if any) of 

the brackets need to be shimmed to allow for a level and 

straight enclosure installation. An enclosure support bar will 

be installed between the two vertical legs of the pedestal 

bracket after the element(s) have been installed.

3.  Locate finned tube element where identified on mechanical 

drawings. Place element slide cradle supports onto element 

where brackets are located. The legs of the element cradles 

are tapered slightly outward so that a friction or 

compression fit will occur and hold them in place when 

pressing the cradles into place between the element fins. 

Place element and element slide cradles onto the ball 

bearings in the bracket and make sweat connections. For 

steel element, apply specified pipe dope or sealing tape for 

threaded connections with the required threaded fittings. 

Check submittal drawings to confirm dimension out from 

wall to center of element and up from finished floor. Once 

the elements are connected into the heating system, a 

standard pressure leak test should be conducted as 

specified by the Mechanical Engineer. For copper tube 

elements, flush the loop or series with system water 

after soldering to neutralize the remaining flux material 

and prevent corrosive action and resulting pinhole 

leaks.

INSTALLATION INSTRUCTIONS 

VERSA-LINE

 

COMMERCIAL FINNED-TUBE RADIATION

JVB-PM/2PM

4.  When the enclosure run is laid out wall to wall with the 

supply and return tube running through the wall, it is typical 

to start and finish the run of enclosure with a “Wall Sleeve". 

This over lapping accessory provides for make-up in the run 

where the wall-to-wall dimension does not coincide with the 

standard enclosure lengths. The slip-jointed enclosures 

interlock with each other along the run. Inside or outside 

corners  are  universal  with  the  pedestal  style  enclosure.                                              

5.  When enclosure is installed short of wall with supply and 

return lines coming out of the floor, end caps will be used to 

terminate the enclosure run at each end. For JVB-PM & 

2PM enclosures, the end caps provided are either left hand 

or right hand and interlock with the enclosure slip-joints. 

6.  If access is needed to air vents or shut off valves, it is 

recommended that a two (2) foot piece of enclosure is 

installed in the run where the device is located. This piece of 

enclosure will act as a valve compartment or access panel.

MAINTENANCE

Before each heating season, remove accessories and 

enclosure panel to inspect finned tube elements for 

accumulation of dust or other debris that may accumulate and 

block airflow between fins. Remove dust and debris from coil 

fins with a vacuum cleaner or compressed air. Inspect for leaks 

or areas of corrosion. It should not be required, but if necessary, 

place a drop of lubricant (machine oil) onto each ball bearing 

(where applicable) located in the water brackets or bracket 

mounted hangers. Replace cover and accessories.

260 North Elm St., Westfield, MA 01085 Tel: (413) 564-5535 Fax: (413) 562-8437

www.sterlingheat.com

Reviews: