Commissioning
Before commissioning, ensure the following:
• Check the mounting and installation.
• Enclosure must not be damaged.
• If necessary, remove foreign bodies.
• Check if the cables have been inserted correctly.
• Check if all screws and nuts have been tightened firmly.
• Check if all conductors have been clamped firmly.
• Check if all prescribed tightening torques have been observed.
9
Maintenance and Repair
9.1
Maintenance
• Consult the relevant national regulations to determine the type and extent of
inspections.
• Adapt inspection intervals to the operating conditions.
At a minimum, check the following points during maintenance work on the device:
• whether the clamping screws holding the cables are securely seated,
• whether the device enclosure and / or protective enclosure have cracks or other visible
signs of damage,
• whether the cable entry seal is damaged,
• whether the permissible temperatures are complied with (according to IEC/EN 60079),
• whether the device is used according to its designated use.
9.2
Maintenance
DANGER
Explosion hazard due to incorrect installation!
Non-compliance results in severe or fatal injuries.
• Check the device for proper installation before commissioning.
• Comply with national regulations.
CAUTION
Risk of electric shock or malfunction of the device due to unauthorized
work!
Non-compliance can result in light injuries!
• Before carrying out work on the device, switch off voltage supply.
• Work performed on the device must only be carried out by
authorized and appropriately trained qualified electricians.
Observe the relevant national regulations in the country of use.