DIGIVEX Little Drive Servoamplifier
75
PVD 3530 GB 01/2005
7. COMMISSIONING - SERVO-CONTROL PARAMETER
SETTING - DETECTING REASONS FOR STOPPAGE
7.1 Start-up Sequence
7.1.1 Preliminary checks
Wiring check
Power and auxiliary connections to DLD.
Reset wiring.
External 24 V supply for brake.
Check the resolver connections.
♦
Motor end
♦
DLD end
Check the power, brake and thermal connections.
♦
Motor end
♦
DLD end
Supply type check
Power: 50/60 Hz, 230 V single or three-phase
Auxiliaries: single-phase 50/60 Hz, 230 V.
Brake supply: 24 V dc ±10% (including oscillation).
Caution:
Before doing any work on the system, make sure the power bus is at 0 V. Wait at least
three minutes after the motors have come to a complete stop before starting work.
Wait for the
7-segment display to go off.
7.1.2 Commissioning with DIGIVEX PC software
Connect the PC via the RS232 serial link.
Energize the auxiliary parts (low levels) alone; 0 is displayed
Go "On line" via the PC, with the PC in interactive mode. Parameter adjustment functions'
connection. If this connection is not carried out:
♦
Check the compatibility of the serial link configuration (PORT, BAUD RATE, etc.)
♦
Check the serial link cable.
♦
Check that you are using the correct interface (DIGIVEX, DLD).
This manual was downloaded on www.sdsdrives.com
+44 (0)117 938 1800 - [email protected]