Chapter 3 - Preparing for Installation
Unpacking the Spectra BlackPearl NAS Solution
• Allow approximately 3 inches (8 cm) of additional depth at the back of the rack for cable
clearance.
• If the rack has a door, allow at least 2 inches (5 cm) of clearance between the front door
frame and the front mounting posts of the rack to allow the door to close over the front
bezel.
• Check your rack’s specifications to make sure it will accommodate the weight and depth
of the BlackPearl NAS chassis.
Notes:
• Using a two-post rack is not supported.
• An enclosed 19-inch, four-post rack is available for purchase from Spectra Logic.
The rack has two doors and removable side panels.
• In earthquake-prone areas, provide restraints as necessary. See the
Site Preparation Guide
for more information.
Unpacking the Spectra BlackPearl NAS Solution
IMPORTANT
Do not unpack a BlackPearl NAS solution if the shipping box shows signs of damage.
Contact both the shipping company and Spectra Logic (see
) to report the problem.
The Spectra BlackPearl NAS solution and its drives are shipped in a cardboard box attached
to a pallet. The only tool needed to unpack them is a pair of scissors.
Save the box, anti-static bags, and foam packaging in case you need to move or ship the
master node later.
January 2022
Installation Guide-Spectra BlackPearl NAS Solution