INSERTING TURBULATORS
1.
Assemble the turbulators together by interlocking the slotted end portions. Slide these into the last tube
section until they are flush with the tube end. Note: Refer to the table below for quantities of turbulators
required for each heater model.
MODEL
2 Ft. Turbulator Sections
PCS-SS 75
5
PCA-SS 100
3
PCA-SS 125
6
PCA-SS 150
4
9.6)
ADDING BODY REFLECTORS
2.
Slide the reflectors through the wire hangers.
3.
The tube at the coupling joints must be covered. Slide the reflectors together and provide an overlap of two
(2”) inches for
each reflector overlap.
4.
Place a reflector retainer at the burner end and after each reflector overlap. Secure the retainers to the tube
using a spring provided with the heater as shown in Det
ail “A”.
Note: The first reflector overlap must be able
to slide for natural expansion and contraction of the heater when in operation. See Detail
“B” for reta
iner
location. The heaters can expand and contract up to 1-
3/4”.
5.
Secure the reflectors as shown in Det
ail “A” using #10 x 1/2” self
-drilling sheet metal screws at the bottom of
each reflector retainer.
6.
Lock the reflectors in place as shown in Detail
“
A
”
using the #10 x 1/2
”
self-drilling sheet metal screws
through the sides of each reflector retainer.
7.
Secure the reflectors at the overlaps shown in Detail
“
C
”
by sliding speed clips onto the reflector edges.
8.
Lock the
first
wire hanger as shown in Detail
“
D
”
by using a reflector/hanger retainer on each side and
securing with (2) #10 x
½”
self-drilling sheet metal screws. Insert the screws from the inside of the reflector.
Summary of Contents for PCA-SS 100
Page 13: ...Form 43343110 12 May 2021 7 1 DIMENSIONS STRAIGHT CONFIGURATION 48 HANGING CENTERS...
Page 14: ...Form 43343110 May 2021 13 7 2 HEATER ASSEMBLY JOINING OF TUBE SECTIONS...
Page 21: ...Form 43343110 20 May 2021...
Page 48: ...Form 43343110 May 2021 47 19 0 TROUBLESHOOTING GUIDE SINGLE STAGE N5 L5...
Page 49: ...Form 43343110 48 May 2021 TROUBLESHOOTING GUIDE SINGLE STAGE CONTINUED...
Page 50: ...Form 43343110 May 2021 49 TROUBLESHOOTING GUIDE SINGLE STAGE CONTINUED...
Page 51: ...Form 43343110 50 May 2021 19 1 TROUBLESHOOTING GUIDE TWO STAGE N7 L7...
Page 52: ...Form 43343110 May 2021 51 TROUBLESHOOTING GUIDE TWO STAGE CONTINUED...
Page 53: ...Form 43343110 52 May 2021 TROUBLESHOOTING GUIDE TWO STAGE CONTINUED...