PREPARATION
-12-
For Machines Mfd. Since 12/20
South Bend Tools
Model SB1108/SB1109
P R E P A R A T I O N
Preparation Overview Required for Setup
The items listed below are required to
successfully set up and prepare this machine for
operation.
For Lifting
• A forklift or other power lifting device rated
for the weight of the machine.
• Lifting Strap or Chain (rated for at least 1000
lbs.)
For Power Connection
• A power source that meets the minimum cir-
cuit requirements for this machine. (Refer to
the Power Supply Requirements on Page
13 for details.)
For Assembly
• Safety Glasses (for each person)
• Straightedge 4' (or longer)
• Dust Collection System
• 4" Dust Hose (for SB1108)
• 4" Hose Clamp (for SB1108)
• 5" Dust Hose (for SB1109)
• 5" Hose Clamp (for SB1109)
• Disposable Rags
• Disposable Gloves
• Cleaner/Degreaser
• Gearbox Oil
• Phillips Head Screwdriver #2
• Open-End Wrench 8mm (for SB1108)
• Open-End Wrench 17mm (for SB1109)
The purpose of the preparation section is to help
you prepare your machine for operation. The list
below outlines the basic process. Specific steps
for each of these points will be covered in detail
later in this section.
The typical preparation process is as follows:
1.
Unpack the machine and inventory the
contents of the box/crate.
2.
Clean the machine and its components.
3.
Identify an acceptable location for the
machine and move it to that location.
4.
Level the machine using the pre-installed
machine mounts.
5.
Assemble the loose components and make
any necessary adjustments or inspections to
ensure the machine is ready for operation.
6.
Connect the machine to the power source.
7.
Test run the machine to make sure it
functions properly and is ready for operation.