  Remove the housing cover.

  Place the instrument on an insulated surface or support 

 

so the sensor does not touch a conductive surface. 

  Apply 12 to 28VDC, and observe the LED. (See 

 on page 2)

NOTE: When the LED is on, it indicates the output is in the normal state 16-20mA.

  Turn the sensitivity adjustment clockwise (up to 25 turns) to increase sensitivity until 

the LED goes out.  

NOTE: Do not turn the sensitivity adjustment past 25 turns! Damage to the unit could result.

  Turn the sensitivity adjustment counterclockwise to decrease sensitivity until the 

LED illuminates. 

Pre-Installation I/O Test and Calibration

651 K9 RF Admittance 

Two Wire Point Level Control

General Instructions

Registered Quality System to ISO 9001

Design and 

specifications are 

subject to change 

without notice. 

For latest revision, go to 

SORInc.com

Table of Contents

Pre-Installation I/O and Calibration ....... 1-2
Installation .......................................3 
Electrical Connections .........................4
Post-Installation Calibration ..................4
SOR RF Probe Grounding Screen ............5
Control Drawings ............................ 6-9
Instructions for EMC .......................... 10
Spare Parts .................................... 10
Information for IEC-Listed Product ......... 10
Maintenance and Troubleshooting ......... 11
Dimensions ................................ 12-13
ATEX and IECEx Marking Details ........... 14
Declaration of Conformity ................... 15

These instructions provide specific information for installation, 
electrical connection, calibration and troubleshooting for the 
651 K9 RF Admittance Two-Wire Point Level Control.

NOTE: If you suspect that a product is defective, contact the factory 
or the SOR

®

 Representative in your area for a return authorization 

number. This product should only be installed by trained and 
competent personnel.

Summary of Contents for 651 K9 RF

Page 1: ...istered Quality System to ISO 9001 Design and specifications are subject to change without notice For latest revision go to SORInc com Table of Contents Pre Installation I O and Calibration 1 2 Installation 3 Electrical Connections 4 Post Installation Calibration 4 SOR RF Probe Grounding Screen 5 Control Drawings 6 9 Instructions for EMC 10 Spare Parts 10 Information for IEC Listed Product 10 Main...

Page 2: ...Usually 1 2 turns will locate the new null point When practical use a small container of actual process material to calibrate the control If the actual process vessel is metal use a metal container coffee can etc and ground it to the instrument housing If the actual process vessel is an insulator such as fiberglass use a plastic container Immerse the sensor in the process material the LED should t...

Page 3: ...zle or half coupling Allow a 4 turn radius See and Sometimes open tanks vats sumps or basins require a locally made bracket mount similar to that shown in See Optional configuration is a raised face or flat face ANSI flange See Form 1100 for selection See g and Orientation The control can be mounted in any position Sensitivity is optimized when the greatest surface area of the sensor is parallel t...

Page 4: ...e to do so could result in severe personal injury or substantial property damage Remove the housing cover Ensure that all wiring conforms to all applicable local and national electrical codes and install unit s according to relevant national and local safety codes Connect the positive loop power wire to the terminal marked Connect the negative loop power wire to the terminal marked Replace the cov...

Page 5: ... SOR Supplied Stilling Well optional Probe Center Conductive Element IMPORTANT Do not provide separate earth grounding for the process connection This can create a parallel grounding circuit that will impair operation and calibration Do not provide separate earth grounding for the process connection This can create a parallel grounding circuit that will impair operation and calibration ...

Page 6: ...6 16 Form 759 04 16 SOR Inc Control Drawing Drawing 9093008 ...

Page 7: ...Form 759 04 16 SOR Inc 7 16 Control Drawing Drawing 9093010 ...

Page 8: ...8 16 Form 759 04 16 SOR Inc Control Drawing Drawing 9093011 ...

Page 9: ...Form 759 04 16 SOR Inc 9 16 Control Drawing Drawing 9093009 ...

Page 10: ...robe wire Short Fat Bead Certificate Number IECEx BAS 05 0054X Issue 2 Standards IEC 60079 0 2011 Ed 6 and IEC 60079 11 2011 Ed 6 Listing Ex ib IIB Tx Gb 40 C Ta 80 C Certificate Number Baseefa 12ATEX0084X Standards IEC 60079 0 2011 Ed 6 and EN60079 11 2012 Condition of Safe Use This apparatus may not be capable of withstanding the insulation test required by Clause 6 4 12 of IEC 60079 11 1999 Thi...

Page 11: ...erial 1 Bad circuit switch 2 The oscillator is not working Call the factory Calibration drifts 1 Sensitivity improperly set 2 Highly conductive product 3 Heavy conductive build up on the sensor 1 Recalibrate according to Post Installation Calibration Instructions on page 3 2 Use sheather sensor 3 Use sheather sensor and periodically remove build up Corroded sensor Process material has chemically a...

Page 12: ...on Proof Integral B C 96 0 3 78 116 7 4 59 A LENGTH PER MODEL NUMBER 19 1 0 75 INACTIVE SHEATH ONLY D INACTIVE SHEATH LENGTH PER MODEL NUMBER 3 4 NPTF ELECTRICAL CONNECTION PROCESS CONNECTION SEE TABLE 1 1 Linear mm inches Drawing 0390654 Dimensions are for reference only Contact the factory for certified drawings for a particular model number SENSOR STYLE D BARE 12 7 0 50 SHEATH 15 9 0 63 BARE WI...

Page 13: ...il 50 8 2 00 31 8 1 25 28 4 1 12 SEE DETAIL A DUAL CABLE PROBE DETAIL DUAL RIGID PROBE DETAIL MINIMUM CLEARANCE HOLE FOR INSTALLATION 54 9 2 16 36 5 1 44 22 2 0 88 D 3 4 16 UNF 2B X 11 1 0 44 Linear mm inches Drawing 0390654 Linear mm inches Drawing 0390654 Dual Cable Probe Detail Dimensions are for reference only Contact the factory for certified drawings for a particular model number ...

Page 14: ...Identification Location of Serial Number First Two Numbers Indicate Year of Manufacture General Information for ATEX Certified Models Location of ATEX Listing Information Drawing 8924119 Drawing 0720527 Manufacturer s Registered Trademark Manufacturer s Registered Trademark ...

Page 15: ...f America April 20 2016 ATEX Directive 2014 34 EU Equipment Intended for use in Potentially Explosive Atmospheres IEC 60079 0 2011 IEC 60079 11 2011 EN 60079 11 2012 II 2G Ex ib IIB T4 Gb 40 C Ta 80 C EC Type Examination Certificate Baseefa 12ATEX0084X IECEx BAS 05 0054X Issued August 16 2005 Baseefa Ltd Notified Body No 1180 Rockhead Business Park Staden Lane Buxton Derbyshire SK17 9RZ United Kingd...

Page 16: ...16 16 Form 759 04 16 SOR Inc 14685West105thStreet Lenexa KS66215 913 888 2630 800 676 6794USA Fax913 888 0767 Registered Quality System to ISO 9001 SORInc com ...