7 Commissioning
7.1 Initial commissioning
7.1.1 Filling in the type plate
Tools:
• Permanent marker
Mark off the installed battery capacity on the type plate on the outside of the
storage system.
The possible battery capacities and corresponding nominal power can be found in
the Technical data [P. 9].
7.1.2 Filling in the commissioning report
The commissioning report needs to be filled in for the initial commissioning.
Complete the commissioning report in the appendix of the document in full.
Make a copy of the filled in commissioning report, the original remains with
the operator.
Send a scan of the commissioning report to the following e-mail address
within 5 working days: [email protected]
7.2 Switching on the storage system
7.2.1 Closing the storage system
Illustration 56: Closing the main cabinet
Close the door of the main cabinet.
Install the two Allen screws on the
left side of the main cabinet.
7.2.2 Switching on the storage system
NOTICE
If the storage system can’t be switched on:
Do not attempt switching on the storage system more than three times.
Contact the service!
ð
Further attempts can damage the battery modules.
Fuse switch F1 establishes the connection between the battery and the inverter.