2. This product can only be installed, commissioned, operated and maintained by technicians who 
    have carefully read and fully understood the user manual. 
3. This product must only be connected with PV modules of protection class II (in accordance with 
    IEC 61730, application class A). PV modules with a high capacitance to ground must only be used 
   

if their capacity does not exceed 1μF.Do not connect any sources of energy other than PV 

 

    modules to the product. 
4. When exposed to sunlight, the PV modules generate dangerous high DC voltage which is present 
    in the DC cable conductors and live components. Touching live DC cable conductors and live 
    components can result in lethal injuries due to electric shock. 
5. All components must remain within their permitted operating ranges at all times. 
6. The product complies with Electromagnetic compatibility 2014/30/EU, Low Voltage Directive   
    2014/35/EU and Radio Equipment Directive 2014/53/EU. 
 
 

 

1. Ensure that the inverter is installed out of the reach of children. 
2. To ensure best operating status and prolonged service life, the 

ambient temperature of the location should be 

40

°

C. 

3. To avoid direct sunlight, rain, snow, pooling of water on the inverter, it is 

suggested to mount the inverter in places which are shaded during the majority of       
the day or to install an external cover that provides shade for the inverter. 
Do not place a cover directly on top of the inverter. 

4. The mounting condition must be suitable for the weight and size of the inverter. The inverter is suitable 

to be mounted on a solid wall that is vertical or tilted backwards 

(Max. 15°). It is not recommended to

 

install the inverter on walls made of plasterboards or similar materials. The inverter may emit noise   

during operation. 
 

 
 
 
5. To ensure adequate heat dissipation, the recommended clearances between the   
    inverter and other objects is shown in the image to the right: 

 

 

 

 

1. 

Use a Φ12mm bit to drill 3 holes at a depth of about 70mm according to the location of the wall

 

mounting bracket. (Figure A) 

2. Insert three wall plugs into the wall and fix the wall mounting bracket to the wall by inserting three   

M8 Screws (SW13). (Figure B) 

3. Hang the inverter to the wall mounting bracket. (Figure C) 
4. Secure the inverter to the wall mounting bracket on both sides using two M4 screws. 

Screwdrivertype:PH2, torque:1.6Nm. (Figure D) 

   

 

 
 
 
 
 
 
 
 
 
 

                                             

 
 

 

 
 
 
 
 
 
 
1. AC cable requirements are as follows. Strip the cable as shown in the figure, and crimp the copper 

wire to the appropriate OT terminal (provided by the customer). 

 
 

 
 
 

Object 

Description 

Value 

External diameter 

20-42mm 

Copper conductor cross-section 

16-50mm

2

 

Stripping length of the insulated conductors 

Matching terminal 

Stripping length of the cable outer sheath 

130mm 

The external diameter of the OT terminal shall be less than 22mm. 

The PE conductor must be 5 mm longer than the L and N conductors. 

Please use a copper - aluminum terminal when aluminum cable is selected. 

2. Remove the plastic AC/COM cover from the inverter, pass the cable through the waterproof 

connector on the AC/COM cover in the wall-mounting accessories package, and retain the 
appropriate sealing ring according to the wire diameter, lock the cable terminals onto the inverter-
side wiring terminals respectively (L1/L2/L3/N/PE,M8/M5), install the AC insulation sheets onto the 
wiring terminals (as shown in Step 4 of the figure below), then lock the AC/COM cover with screws 
(M4x10), and finally tighten the waterproof connector. (Torque M4:1.6Nm; M5:5Nm; M8:12Nm; 
M63:SW65,10Nm)

 

 
 
 
 
 
 
 
 

3. If required, you can connect a second protective conductor as equipotential bonding. 
     
 
 
 
 
 
 
 

 

 

   
 
 
 
 
 
1. 

Please refer to “DC Connector Installation Guide”.

 

2. Before DC connection, insert the DC plug connectors with 
    sealing plugs into DC input connectors of the inverter to   
    ensure protection degree. 
 
 
 

 

 

 

 

 

Object 

Description 

M5×12 screw

 

Screwdriver type: PH2, torque: 2.5Nm 

OT terminal lug 

Customer provided, type: M5 

Grounding cable 

Copper conductor cross-section: 16-25mm

2

 

 

 

 

 

 

 

 

Figure A 
 

Figure B 
 

I. Safety Instruction 

II. Mounting environment 

III. Scope of delivery 

IV. 

Inverter’s mounting

 

Figure C 
 

Figure D 
 

V.AC connection 

All electrical installations must be done in accordance with all local and national rules. 

Make sure that all DC switches and AC circuit breakers have been disconnected before establishing 

electrical connection. Otherwise, the high voltage within the inverter may lead to electrical shock. 

In accordance with safety regulations, the inverter need be grounded firmly. When poor ground   

connection (PE) occurs, the inverter will report PE grounding error. Please check and ensure that   
the inverter is grounded firmly or contact AISWEI service. 

VI.DC connection 

Make sure PV modules have good insulation against ground. 

On the coldest day based on statistical records, the Max. open-circuit voltage of the PV modules 

must not exceed the Max. input voltage of the inverter. 

Check the polarity of DC cables. 

Ensure that DC switch has been disconnected. 

Do not disconnect DC connectors under load. 

VII. Communication setup 

Separate communication cables from power cables and serious interference sources. 

The communication cables must be CAT-5E or higher-level shield cables. Pin assignment complies 

with EIA/TIA 568B standard. For outdoor use, the communication cables must be UV-resistant. The 
total length of communication cable cannot exceed 1000m. 

If only one communication cable is connected, insert a sealing plug into the unused hole of sealing   

ring of the cable gland. 

Before connecting communication cables, ensure the protective film or communication plate attached to the 

 communication opening on the inverter is sealed tightly. 