![SOLARFOCUS octoplus Installation Manual Download Page 19](http://html1.mh-extra.com/html/solarfocus/octoplus/octoplus_installation-manual_1313809019.webp)
Installation
Installation manual
octo
plus
19
Fig. 5-12
Prepare downpipe insert
Bend the finger of the downpipe
insert
1
to an angle of ~80°.
Tip: use pliers.
Fig. 5-13
Install downpipe insert and pipe
clamp
Position pipe clamp
1
including
downpipe insert
2
to the down-
pipe bracket.
Check
3
: The finger of the down-
pipe insert must be aligned (in
plan view) to the boiler back
panel.
Fig. 5-14
Installing the pellet feeder unit
Slide the pellet feeder unit
1
into
the intermediate pellet store.
Connect the two connection spig-
ots with the pipe clamp
2
.
Attention!
Open filling chamber
door
3
and reach into the downpipe
from below:
Check for correct
seat / orientation of the downpipe
insert.
Check horizontal / vertical orien-
tation of the intermediate pellet
store, readjust if necessary.
Tighten up screws on the inter-
mediate pellet store console
4
.
Summary of Contents for octoplus
Page 40: ...Initial commissioning 40 Installation manual octoplus 8 1 Commissioning log...
Page 41: ...Initial commissioning Installation manual octoplus 41...
Page 42: ...Initial commissioning 42 Installation manual octoplus 8 2 Customer service order form...
Page 45: ...System schematic Installation manual octoplus 45...
Page 46: ...System schematic 46 Installation manual octoplus...
Page 47: ...System schematic Installation manual octoplus 47...