Setup StorEdge Operating Mode
8.1
Turn ON the inverter.
8.2
Use the status screens to check charge or discharge according to the current condition.
8.3
Set up the operating mode according to one of the following options:
Maximize Self Consumption
7.3.1
Select Power Control > Energy Manager > Energy Control > Max self-Consume
Charge/Discharge Profile Programming
7.3.2
Select Power Control > Energy Manager > Energy Control > Time of Use
9
Battery State of Energy (SOE) Check
9.1
Turn ON the inverter.
9.2
Check battery’s SOE value on the inverter display.
If the SOE is below 10%, immediately check that the inverter is successfully charging the battery.
9.3
If the battery does not charge:
* Record the date of manufacture, which is embedded in the part number. The part number is printed on a label on the control panel of the battery
XXXXXXXXXXXXXYYMMDDXXX, Example: R15563P3SSEG1170328032, YY=17 MM=03 DD=28
* Contact your LG Chem regional customer service representative for assistance.
10
Basic System Operation (optional)
10.1
Turn the AC power to the inverter OFF, and verify that the inverter has switched to backup mode.
10.2
Turn the AC power to the inverter ON, and verify that the inverter is operating properly.
Support and Contact Information
If you have technical queries concerning our products, please contact us:
USA and Canada: +1 510 498 3200
Worldwide:
+972 073 2403118
Fax:
+1 (530) 273-2769
Email: