6. Select the following to configure the connection:
l
Server
è
LAN
l
RS485-1
è
Protocol
è
SolarEdge Master
l
RS485-1
è
Slave Detect
The system starts automatic detection of the SolarEdge slave inverters connected to the master
inverter. The inverter should report the correct number of slaves. If it does not, verify the connections
and terminations.
RS485-1
Protocol
SolarEdge (Master)
›
Device ID
1
Slave Detect
3 Slaves
›
Long Slave Detect
3 Slaves
›
Slave List
3 Slaves
›
7. To check the slave IDs and last communication time, select
RS485-1
è
Slave List
.
8. Verify the connection of the master to the SolarEdge monitoring platform, as described in the next
section.
Verifying the Connection
After connecting and configuring a communication option, perform the following steps to check that
the connection to the monitoring server has been successfully established.
1. If the Connection Unit cover is not closed, close it: Attach the Connection Unit cover and secure it by
tightening the screws with a torque of 10.3 N*m/ 7.5 lb.*ft.For proper sealing, first tighten the corner
screws and then the two central screws.
2. Access the Status screen:
a. If not already ON - turn ON AC to the inverter by turning ON the circuit breaker on the main
distribution panel.
b. If not already ON - move the Connection Unit switch to the ON position.
c. Open SetApp and follow the instructions on the screen (scan the inverter bar-code; move the
ON/OFF/P switch to P position (for less than 5 sec) and release).
The mobile device creates a Wi-Fi connection with the inverter and displays the inverter main
Status screen.
Chapter 6: Setting Up Communication
Three Phase Inverter with synergy technology Guide MAN-01-00402-1.1