1. From the
Commissioning
screen select
Country & Grid
.
2. From the
Country & Grid
drop-down list, select the required option and tap
Set
Country & Grid
.
3. From the
Language
drop-down list, select your language and tap
Set Language
.
Pairing
1. From the
Commissioning
menu, select
Pairing
.
2. Tap
Start Pairing
.
3. When Pairing Complete is displayed, the system startup process begins:
Since the inverter is ON, the Power Optimisers start producing power and the
inverter starts converting AC.
WARNING!
When you turn ON the ON/OFF/P switch, the DC cables carry a high Voltage
and the Power Optimisers no longer output a safe output.
When the inverter starts converting power after the initial connection to the AC, the
inverter enters Wake up mode until its working voltage is reached. This mode is
indicated by the flickering green inverter LED.
When working voltage is reached, the inverter enters Production mode and
produces power. The steadily lit green inverter LED indicates this mode.
4. Tap
OK
to return to the
Commissioning
menu.
Communication
Communication settings can be configured only after communication connections are
complete. Refer to
Setting Up Communication with the Monitoring Platform on page 37.
Select
Monitoring Communication
to configure communication with the
monitoring platform.
Select
Site Communication
to configure communication between multiple
SolarEdge devices or external non-SolarEdge devices, such as batteries or loggers.
Chapter 6: Activating, Commissioning and Configuring the System
50
Three Phase Inverter with SetApp Configuration