Chapter 6: Activating, Commissioning and
Configuring the System
After the solar system is installed, it is important to activate and commission the solar
system. Activation and commission of the system is performed using the inverter
SetApp mobile application.
During the activation and commissioning, the inverter discovers and communicates
with all connected components in the solar system, such as: optimizers, peripheral
communication devices and other linked inverters. When commissioning is performed,
the user is required to set the grid parameters and backup Voltage information (if used).
Before starting the activation and commissioning, verify the all the communication
hardware is properly connect. For communication options, refer to:
Communication with the Monitoring Platform on page 37.
Before arriving at the site, download SolarEdge SetApp application to your mobile
device from Apple App Store or Google Play .
Before activation and commissioning, download the SetApp application from:
For downloading SetApp, Internet connection, one-time registration and logging are
required. No registration is required for using the SetApp.
Step 1: Activating the Installation
During system activation, a Wi-Fi connection is created between the mobile device and
the inverter and the system firmware is upgraded.
Before activation
Download, register (first time only) and login to SetApp on your mobile device.
Verify that the application is updated with the latest version.
Chapter 6: Activating, Commissioning and Configuring the System
48
Three Phase Inverter with SetApp Configuration
Summary of Contents for SE15K-AU