2. Loosen the screws on the front cover of the Safety Switch , as shown below:
Figure 13: Opening the Safety Switch cover
3. Remove the Safety Switch cover.
4. Open the required AC and DC conduit drill guides according to the conduits used in
the installation: The drill guides are located at the bottom, back and sides of the
enclosure, each with two sizes: ¾'' and 1''. Open the required pair, taking care not
to interfere with any of the internal components. It is recommended to use a Unibit
drill.
Figure 14: Safety Switch drill guides
NOTE
Unused conduit openings and glands should be sealed with appropriate seals.
Chapter 3: Installing the Inverter
35
Mounting the Inverter
The inverter is typically mounted vertically, and the instructions in this
section are applicable for vertical installation. Some three phase inverter
models can be installed horizontally (above 10° tilt) as well as vertically,
and at any tilt over 10° up to 90°. For information and instructions for
horizontal mounting refer to
http://www.solaredge.com/sites/default/files/application_note_horizontal_mounting_of_three_
Three
Phase
System
Installation
Guide
MAN-01-00527-1.