Chapter 2: Construction of power optimizers
SolarEdge Installation Guide - MAN-01-00060-2.6
13
Step 2, Connecting a module to an optimizer
power
•
Connect the output connector Plus (+) of the module to the input connector Plus (+) of the power optimizer.
•
Connect the output connector Minus (-) of the module to the input connector Minus (-) of the power
optimizer.
Figure 1: Connectors of the power optimizer
NOTE :
Images are for illustrative purposes only. Refer to the label on the product to identify the input over and under and output connectors.
Step 3, Connecting Power Optimizers
channels
You can build strings in parallel of unequal length, that the number of power optimizers on each channel may be
different. maximum and minimum chain lengths are shown in the data sheet of power optimizers. Refer to the
SolarEdge site designer for verification of the chain length.
NOTE :
The string length must not exceed 300m from the CC + to CC UPS. Use DC cables of 4 mm² minimum.
1
Connect the output connector Minus (-) of the first channel power optimizer
1
Connect the output connector Minus (-) of the first channel power optimizer
output connector Plus (+) of the second chain power optimizer.
Exit
Input - Connect the module
+
-
-
+
Mounting Bracket