follows. For general DIP switch guidelines, see
a. For the meter closest to the inverter, the meter should
be set for No Termination. Both switch 1 and switch 2
should be in the UP position.
b. For the meter furthest from the inverter, the meter
should be set for Termination. Both switch 1 and
switch 2 should be in DOWN position.
4. Set the meters' address DIP switches as follows. For general
DIP switch guidelines, see "DIP Switches" on page 17.
a. For one meter, set the address DIP switches for
Modbus Address 1: Set switch 1 to UP, and set
switches 2 and 3 to DOWN.
b. For the other meter, set the address DIP switches for
Modbus Address 2: Set switch 1 to DOWN, set switch 2
to UP, and set switch 3 to DOWN.
Revenue Grade Energy Meter with Modbus Connection Installation Guide MAN-01-00609-1.0
56
Connecting Two Meters