Ext. Production
: The meter is used for export limitation
with 3rd party generators and for AC coupling with
non-SolarEdge inverters.
6. Select Meter Protocol, and select SolarEdge.
7. Select
Device ID
and enter the Modbus address
corresponding to the ID DIP switch settings on the meter.
8. Select
CT Rating
and enter the current transformer's rating
in amperes.
9. Select Grid Topology and select WYE or Delta, in
accordance with grid and meter type requirements.
10. If relevant, select PT Scaling and set the potential
transformer ratio. The default value is 1.
To verify the meter connection using SetApp:
1. From the SetApp main menu, select Status.
2. On the Status page, scroll down to the Communication
section and view the current connection state.