To configure the SolarEdge meter using SetApp:
1. From the SetApp main menu, select Communication, and
select the port to which the meter is connected - RS485-1
or RS485-2.
2. Select Protocol -> Modbus (Multi-Device)
3. Return to the RS485-x Menu and select Add Modbus
Device -> Meter. A meter identified as "Meter n" (where n
= 1, 2, 3...) is created. The RS485-x Menu reappears.
4. Select Meter n. The RS485-x Meter n Menu appears.
5. Select Meter Function, and choose one of the following
options:
Inverter Production:
The meter is installed at the
inverter output and reads the energy produced by the
inverter.
Import
: The meter is installed at the grid
connection point and reads pulses from both
directions - export and import energy.
Consumption
: The meter is installed at the load
consumption point and reads the energy consumed by
the site.
Site Production:
The meter is installed at the inverter
output and reads the energy produced by inverters at
the site.
Revenue Grade Energy Meter with Modbus Connection Installation Guide MAN-01-00609-1.0
32
Device Configuration