Chapter 5: Activating, Commissioning and
Configuring the System
After the solar system is installed, it is important to activate and commission the solar
system. Activation and commission of the system is performed using the inverter
SetApp mobile application.
The solar system can be activated and commissioned in the following stages of system
stage:
On-grid: The inverter is connected to a utility grid
Pre-commissioning (Off-grid): The inverter is not connected to a grid to enable:
-Early validation and fault detection of system components, such as inverters, Power
Optimiser, PV modules before activation
- Ensure system integrity before connecting to the grid
During the activation and commissioning, the inverter discovers and communicates
with all connected components in the solar system, such as: optimizers, peripheral
communication devices and other linked inverters. When commissioning is performed,
the user is required to set the grid parameters and backup Voltage information (if used).
Before starting the activation and commissioning, verify the all the communication
hardware is properly connect. For communication options, refer to:
Communication with the Monitoring Platform on page 50.
Before arriving at the site, download SolarEdge SetApp application to your mobile
device from Apple App Store or Google Play .
Before activation and commissioning, download the SetApp application from:
For downloading SetApp, Internet connection, one-time registration and logging are
required. No registration is required for using the SetApp.
Chapter 5: Activating, Commissioning and Configuring the System
43
Three Phase Inverters with Synergy Technology