System Setup and Operation Manual for the Solar Stik G-BOSS E Light HPS
PRELIMINARY
“Overload” Conditions
Overloading of the System can occur under the following conditions:
• Load AC power demand is greater than the inverter’s rated output.
• Load AC and DC power demand is greater than the connected AC source (generator or grid/
utility).
• Load AC power demand is greater than the AC INPUT setting, which may cause the PRO-Verter
to disconnect from the AC source when in pass-through (charging) mode.
• Load AC and DC power demand is greater than the output of the connected AC source
(generator or grid utility), causing it to shut down.
In each of these scenarios, the solution is simply a reduction in the total load demand (AC and DC).
Use the AC and DC METERS to confirm the load is reduced to prescribed levels and proceed with
normal operation.