103
17. POINT PROJECTION
• It is also possible to perform point projection measurement by pressing
[P-PROJ] when allocated to the OBS mode screen.
Allocating the function key: "31.3 Allocating Key Functions"
Before performing point projection, the baseline must be defined.
PROCEDURE
1.
Define the baseline.
2.
Select "Point Projection" in <Point
Projection>.
3.
Enter the point coordinate.
• Press [MEAS] to observe the
point to project.
• The tilt screen is displayed if the
instrument is out of level.
Level the instrument.
• Press [REC] to record the data
as a known point.
Recording method:
"29.1 Registering/Deleting
Known Point Data"
17.2 Point Projection
Stn. Orien.
Define baseline
Point projection
Point projection
P o i n t p r o j e c t i o n
N p :
E p :
Z p :
1 2 . 1 5 2
1 0 3 . 5 1 4
1 0 1 . 4 2 3
C
REC
LOAD
MEAS
OK