HYD 3K~6K-EP
User manual
Copyright © Shenzhen SOFARSOLAR Co., Ltd
。
- 3 -
All installation accomplished only by professional electrical
engineer!
Must be trained;
Completely read the manual operation and understand
relevant matter.
Warning
Get permission from the local electrical gird operator,
complete all electrical connections by professional electrical
engineer, then connect inverter to electrical grid.
Attention
It’s forbidden to remove the tamper evident label, or open the
inverter. Otherwise Sofarsolar will not provide warranty or
maintenance!
Note
Operation
Touching the electrical grid or the terminal of the equipment
may lead to electrocution or fire!
Don’t touch the terminal or conductor connected to the
electrical grid.
Pay attention to any instructions or safety documents related to
grid connection.
Danger
Some internal components will be very hot when inverter is
working. Please wear protective gloves!
Attention
Maintenance and repair
Before any repair work, turn OFF the AC circuit breaker
between the inverter and electrical grid first, then turn OFF the DC
switch.
After turning OFF the AC circuit breaker and DC switch, wait
for 5 minutes at least before carrying out any maintenance or repair
work.
Danger
Inverter should work again after removing any faults. If you
need any repair work, please contact with the local authorized
service center.
Can’t open the internal components of inverter without
authorized. Shenzhen SOFARSOLAR Co., Ltd. Does not take any
responsibility for the losses from that.
Attention
EMC / noise level of inverter
Electromagnetic compatibility (EMC) refers to that one electrical equipment
functions in a given electromagnetic environment without any trouble or error, and
impose no unacceptable effect upon the environment. Therefore, EMC represents
the quality characters of an electrical equipment.The inherent noise-immune
character: immunity to internal electrical noise.External noise immunity: immunity