Installation and Commissioning Guide DIRIS DigiBOX A
Ref: dcg_A402019us.rev1 Page 5/15
SOCOMEC PM
Installation and Commissioning Guide DIRIS DigiBOX A
2. Conduit Hole
The DIRIS DigiBOX A is shipped without the conduit holes; they will need to be cut on the left side, right side,
and/or the top. See the below drawings for recommended conduit hole locations.
1. Open the enclosure door, unscrew the two right ride screws, and lift the metal plate.
2. Cut the conduit holes only in the locations where conduit fittings will be installed. Conduit hole templates can
be found within the black bag that comes in the box.
3.
To maintain the enclosure’s environmental rating, the installer must use conduit hubs/fittings* with the same
environmental rating as the enclosure.
4. Maintain spacing of at least ½ inch between conduit hubs/fittings and uninsulated live conductors.
5.
Use “Grounding” conduit fittings* with built-in set screws. Run insulated copper conductors, 16awg or thicker,
from fittings to spar ground terminal blocks.
6. Route incoming voltage conductors at least ¼ inch away from current sensor and signal conductors. Route
current sensor conductors at least ¼ inch away from communication conductors.
7. Use cable ties to secure conductors to each other and to maintain spacing.
Figure 1: Recommended conduit hole locations.
*not supplied by Socomec