3-1
Chapter 3: Installing the Switch
Selecting a Site
Switch units can be mounted in a standard 19-inch equipment rack or on a flat
surface. Be sure to follow the guidelines below when choosing a location.
• The site should:
- be at the center of all the devices you want to link and near a power outlet.
- be able to maintain its temperature within 0 to 50 °C (32 to 122 °F) and its
humidity within 10% to 90%, non-condensing
- provide adequate space (approximately two inches) on all sides for proper air
flow
- be accessible for installing, cabling and maintaining the devices
- allow the status LEDs to be clearly visible
• Make sure twisted-pair cable is always routed away from power lines, fluorescent
lighting fixtures and other sources of electrical interference, such as radios and
transmitters.
• Make sure that the unit is connected to a separate grounded power outlet that
provides 100 to 240 VAC, 50 to 60 Hz, is within 2 m (6.6 feet) of each device and
is powered from an independent circuit breaker. As with any equipment, using a
filter or surge suppressor is recommended.
Ethernet Cabling
To ensure proper operation when installing the switch into a network, make sure that
the current cables are suitable for 10BASE-T, 100BASE-TX or 1000BASE-T
operation. Check the following criteria against the current installation of your
network:
• Cable type: Unshielded twisted pair (UTP) or shielded twisted pair (STP) cables
with RJ-45 connectors; Category 3 or better for 10BASE-T, Category 5 or better
for 100BASE-TX, and Category 5, 5e or 6 for 1000BASE-T.
• Protection from radio frequency interference emissions
• Electrical surge suppression
• Separation of electrical wires (switch related or other) and electromagnetic fields
from data based network wiring
• Safe connections with no damaged cables, connectors or shields
Summary of Contents for SMC TigerSwitch 10/100 SMC6110L2
Page 2: ......
Page 12: ...viii...
Page 14: ...x...
Page 24: ...Introduction 1 6 1...
Page 36: ...Installing the Switch 3 8 3...
Page 44: ...Making Network Connections 4 8 4...
Page 54: ...Specifications C 4 C...
Page 56: ...Ordering Information D 2 D...
Page 63: ...Index Index 3 V VLANS tagging 2 5 W web based management 1 2...
Page 64: ...Index Index 4...
Page 65: ......