Connect the armature wiring to the terminal block according to the amperage rating
listed on the motor. Make sure to set the DIP switch to the value that matches the
amperage rating.
Figure 7: DIP Switch
If the encoder has not been connected, connect the encoder to TB1 using the color
codes provided by the manufacturer or the reference tables in the manual.
Figure 8: Encoder Connection
Apply the control and three-phase power. Verify that the control power is between 103
VAC and 126 VAC.
Press the RESET push button on the front of the power cube and observe the drive
power-up sequence. See Drive Power-Up Sequence.
Drive Power-Up Sequence
The power-up sequence can be observed by monitoring the Standard Control/Display Unit
(SCDU) on the front of the power cube.
When power is initially applied, all segments on the digital LED display and all of the
LEDs come on for about 1 second.
The LEDs and display should turn off. The drive performs internal checks. The SCDU
displays tESt while a self-test is being performed.