(First) Commissioning
Technical Description
SBU2200-TEN083320
87
10.2 Starting the Quick Configuration Guide (QCG)
The QCG is automatically activated during the
initial
startup of the device.
1. Insert the NH fuse into the BatFuse or connect the DC disconnector of the BatFuse.
2. Turn on the Sunny Backup 2200.
Push the DC start button on the Sunny Backup 2200.
3. The Sunny Backup 2200 initiates the startup phase.
Wait for the following displays.
4. As soon as the startup phase is finished, the
message "To init system hold <Enter>" is displayed.
5. Press the button of the Sunny Remote Control 1 and
hold it until three acoustic signals have been
emitted.
6. Release the button.
7. You are now in the Quick Configuration Guide
(QCG).
You can choose between the following options by
turning the button:
•
"Start System"
(if you have accidentally accessed the QCG and only would like to restart the
system)
Information
When starting the QCG, all parameter values are automatically preset! This makes efficient
operation possible with very little effort.
Initial Start-up
When starting the Sunny Backup 2200 for the first time, the QCG will be activated
automatically. If this is the case, please skip down to item 6; otherwise, follow the list
provided below.