6 Maintenance
SMA Solar Technology AG
Maintenance Manual
SCCP-JP-B1-WA-en-23
44
Replace GFDI / ABB circuit breaker
After 100 trippings due to short circuit
or
after number of switching cycles: 7000
• Contact Service.
Replace Remote Switch Unit of the GFDI
Number of switching cycles: 7000
• Contact Service.
6.3.3
Repairs every 10 Years
Task
Comment
Replace 24 V power supply units
• Contact Service.
Replace 24 V buffer power supply unit
• Contact Service.
Replace the fans of the AC disconnection unit*
• Contact Service.
* for Sunny Central 500CP-JP, 800CP-JP and 1000CP-JP
6.3.4
Repairs every 12 Years
Replacement intervals for order option "Q at Night"
The replacement intervals are halved for order option "Q at Night".
Task
Comment
Replace interior fan in the inverter cabinet
• Contact Service.
Replace the inverter bridge fan
• Contact Service.
6.4
Maintenance Work
6.4.1
Maintenance work with supply voltage present
6.4.1.1
Checking the Fans
DANGER
Danger to life due to electric shock or electric arc if live components are touched
• Switch off the inverter and wait at least 15 minutes before opening it to allow the capacitors to discharge
completely.
• Disconnect the inverter (see Section 4, page 25).
Procedure:
1. Switch the inverter to
Stop
.
2. Connect the supply voltage (see Section 4.3.1, page 27).
☑ The fans start to run for a few moments.
✖ The fans do not start up?