7
2 – Installation and Pre Operation
2.1 Installation
2.1.1 Placing the equipment
The equipment must be installed over a firm and level working surface. See below drawing
the recommended area
805mm
735mm
Installation
Area
FRONT
2.1.2 Electric Installation
The equipment has been designed to operate 220 Volts. When you receive the equipment
check the voltage indicated on the cord label
The power plug has 3 pins the middle pin is the ground . All the 3 pins must be properly
connected.
IMPORTANT
Make sure the network voltage is the same as indicated on the Cord label
2.2 Pre Operation
Before to use the equipment all the parts which could get into contact with the product
to be processed shall be washed with water and neutral soap ( see item 3.3 Cleaning and
Sanitizing ).
Make sire the equipment is firm on its working position.