Acceptance test summary
The purpose of this Harbour Acceptance Test is to verify that the SU90 system provided
to the vessel is correctly installed, and fully functional. This acceptance test summary
is provided to offer an overview of the functions and items that need to be tested.
References are made to the individual chapters in this Harbour Acceptance Test.
Procedure
1
Record the software and hardware items that are included in the test.
•
Hardware and software registration, page 9
2
Do a visual inspection of each unit that is comprised by the SU90 delivery.
•
3
Test the main functionality of the SU90.
•
Testing the SU90 operational functionality, page 29
4
Test the interfaces between the SU90 and relevant external devices and/or sensors.
•
Testing the interfaces with peripheral devices, page 40
5
Make sure that all the relevant installation parameters have been defined correctly.
•
Verifying the installation parameters, page 49
6
When all the tests have been successfully concluded, open the
Customer acceptance
form, and fill it in with the relevant signatures.
•
Customer acceptance form, page 56