88/148
Siemens Building Technologies
Commissioning instructions OZW775 V2.01
CE1C5663en
HVAC Products
Further commissioning steps
22.06.2012
5.2 Wiring
test
5.2.1 Wiring test active "Yes / No"
The reference data point "Wiring test active" is displayed only if the reference data point
"Commissioning mode = On" is set.
1. Select
Applications > Popcard…
and check for "Commissioning mode = On".
2. In the menu tree, select
Wiring test
and reference data point "Wiring test active".
3. Double-click "Wiring test active" to open a dialog box. Select
Yes
and click
OK
to enter the value.
After you complete the wiring and communication tests, you must reset the reference
data point to "Wiring test active = No".
Wiring test
active = Yes
Workflow
Wiring test
active = No