Plus+ Sealed Base Kit Components and Earthing Mechanism
6.6.3
Terminate the cable armouring (Standard ST950 Stool)
The outer sheathing must be stripped to expose the armouring. It is suggested that between
15mm and 30mm of the inner sheathing Is left above the CET bar. A further conductor length
must also be allowed, sufficient to reach the CTB terminal blocks via the proper routing.
The cable is inserted in the CET ring and the armoured wires are bent outwards and down against
the ring. A hose clip is then placed over the armoured wires and tightened up. The outer cable
sleeve must be stripped from the armouring approx. 0 to 2mm below the level of the CET ring.
See Figure 50 for details.
The inner sheathing is removed to expose the individual leads, which are connected to associated
terminals, leaving sufficient spare length for re-making off the ends should this become
necessary.
Shim to suit
different cable
diameters.