Commissioning
6.13 Zero point adjustment
FC410 with Modbus
Operating Instructions, 02/2016, A5E33120874-AC
65
Drop-down menus
Table 6- 1
Device menus
Device menus
Description
Communication Path
Shows the communication interface (Modbus RTU)
Download to Device
Downloads all writable parameters to the device
Upload to PC/PG
Uploads all parameters from the device to the parameter
table
Update Diagnostic Status
Reads current diagnostic status from the device and
updates the diagnostic status icon
Communication
Sets communication parameters, for example baud rate
Wizard - Quick Start
Guide for a quick commissioning
Wizard - Zero Point Adjustment
Guide for zero point adjustment (automatic and manual)
Totalizer (online dialog)
Controlling massflow totalizer
Maintenance (online dialog)
Setup of maintenance functions
Simulation (online dialog)
Simulation of process values
Access Management
Possibility to upgrade access level from User to Expert
and to change PIN code for Expert level
Table 6- 2
View menus
View menus
Description
Process Variables (online dialog)
Shows all process values
Device Diagnostic (online dialog)
Shows all diagnostics information (alarms and diagnos-
tics parameters)
Toolbar (online dialog)
Shows/hides the toolbar
Status Bar
Shows/hides the status bar
Update
Updates the content of the active window
6.13
Zero point adjustment
The flowmeter system is optimized through a zero point adjustment.
Performing a zero point adjustment
Note
Preconditions
Before a zero point adjustment is initiated, the pipe must be flushed, filled and at an absolute
flowrate of zero preferably also at operating pressure and temperature.