3 Mounting and Commissioning
240
7ST6 Manual
E50417-G1176-C251-A3
3.3
Commissioning
WARNING!
Warning of hazardous voltages when operating electrical devices
Non-observance of the following measures can result in death, personal injury or sub-
stantial property damage.
Only qualified people shall work on and around this device. They must be thoroughly
familiar with all warnings and safety notices in this instruction manual as well as with
the applicable safety steps, safety regulations, and precautionary measures.
The device is to be earthed to the substation earth before any other connections are
made.
Hazardous voltages can exist in all switchgear components connected to the power
supply and to measurement and test circuits.
Hazardous voltages can be present in the device even after the power supply voltage
has been removed (capacitors can still be charged).
After removing voltage from the power supply, wait a minimum of 10 seconds before
re-energizing the power supply. This wait allows the initial conditions to be firmly es-
tablished before the device is re-energized.
The limit values given in Technical Data must not be exceeded, neither during testing
nor during commissioning.
When testing the device with secondary test equipment, make sure that no other mea-
sured values are connected and that the TRIP command lines and possibly the
CLOSE command lines to the circuit breakers are interrupted, unless otherwise spec-
ified.
DANGER!
Hazardous voltages during interruptions in secondary circuits of current trans-
formers
Non-observance of the following measure will result in death, severe personal injury
or substantial property damage.
Short-circuit the current transformer secondary circuits before current connections to
the device are opened.
For the commissioning switching operations have to be carried out. A prerequisite for
the prescribed tests is that these switching operations can be executed without
danger. They are accordingly not meant for operational checks.
www
. ElectricalPartManuals
. com