Direction Check with Load Current
≥ 10 % of Load Current
The correct connection of the current and voltage transformers is tested via the protected line using the load
current. For this purpose, connect the line. The load current the line carries must be at least 0.1 ·
Ι
Nom
. The
load current should be in-phase or lagging the voltage (resistive or resistive-inductive load). The direction of
the load current must be known. If there is any doubt, network or ring loops should be opened. The line
remains energized during the test.
The direction can be derived directly from the operational measured values. Initially the correlation of the
measured load direction with the actual direction of load flow is checked. In this case the normal situation is
assumed whereby the forward direction (measuring direction) extends from the busbar towards the line
P positive, if active power flows into the line,
P negative, if active power flows towards the busbar,
Q positive, if reactive power flows into the line,
Q negative, if reactive power flows toward the busbar.
[lastscheinleistung-110402-wlk, 1, en_US]
Figure 3-37
Apparent Load Power
All signs of powers may be inverted deliberately. Check whether polarity is inverted in address 1108
P,Q
sign
in the
P.System Data 2
. In that case the signs for active and reactive power are inverse as well.
The power measurement provides an initial indication as to whether the measured values have the correct
polarity. If both the active power and the reactive power have the wrong sign and 1108
P,Q sign
is set to
not reversed
, the polarity according to address 201
CT Starpoint
must be checked and corrected.
However, power measurement itself is not able to detect all connection errors. For this reason, directional
messages should be generated by means of the directional overcurrent protection. Therefore, pickup thresh-
olds must be reduced so that the available load current causes a continuous pickup of the element. The direc-
tion reported in the messages, such as
Phase A forward
or
Phase A reverse
must correspond to the
actual power flow. Be careful that the “Forward” direction of the protective element is in the direction of the
line (or object to be protected). This is not necessarily identical with the direction of the normal the power
flow. For all three phases, the directional messages to the power flow must be reported properly.
If all directions differ from each other, individual phases in current or voltage transformer connections are
interchanged, not connected properly or phase assignment is incorrect. After isolation of the line and short-
circuiting of the current transformers the connections must be checked and corrected. The measurements
must then be repeated.
Finally, switch off the protected power line.
i
i
NOTE
Reset the pickup values changed for the check to valid values.
3.3.9
Mounting and Commissioning
3.3 Commissioning
426
SIPROTEC 4, 7SJ62/64, Manual
C53000-G1140-C207-8, Edition 08.2016
Summary of Contents for SIPROTEC 4
Page 8: ...8 SIPROTEC 4 7SJ62 64 Manual C53000 G1140 C207 8 Edition 08 2016 ...
Page 18: ...18 SIPROTEC 4 7SJ62 64 Manual C53000 G1140 C207 8 Edition 08 2016 ...
Page 30: ...30 SIPROTEC 4 7SJ62 64 Manual C53000 G1140 C207 8 Edition 08 2016 ...
Page 540: ...540 SIPROTEC 4 7SJ62 64 Manual C53000 G1140 C207 8 Edition 08 2016 ...
Page 594: ...594 SIPROTEC 4 7SJ62 64 Manual C53000 G1140 C207 8 Edition 08 2016 ...
Page 720: ...720 SIPROTEC 4 7SJ62 64 Manual C53000 G1140 C207 8 Edition 08 2016 ...