Manual
Commissioning Manual, 05/2008, 6FC5397–4CP10–4BA0
121
Power-On and Power-Up
5
5.1
Preparing for commissioning
5.1.1
Checklist
SINUMERIK 840Di sl
The following checklist will help you to commission the supplied components without undue
problems and ensure a high availability on your product:
●
When handling the components, all ESD measures are observed.
●
All screws are tightened with their prescribed torque.
●
All connectors are plugged correctly and locked/screwed.
●
All components are grounded and connected to shields.
●
The load capacity of the central power supply is taken into account.
Drives
Additional points should be observed depending on the drive system used. For detailed
information, please refer to:
●
SINAMICS S120
Commissioning Manual, Section "Prerequisites for startup"
●
SIMODRIVE 611 universal
/FBU/ Function Manual SIMODRIVE 611 universal, Section "General information on
startup"
Limit values
All components are dimensioned for defined mechanical, climatic and electrical
environmental conditions. No limit value may be exceeded, neither during operation, nor
during transportation.
In particular, the following must be observed:
●
Power supply conditions
●
Pollution burden