Commissioning
4.5 Commissioning with STARTER
Inverter with CU240B-2 and CU240E-2 Control Units
84
Operating Instructions, 07/2010, FW 4.3.2, A5E02299792B AA
● In the control panel, click on the "Assume control priority" button.
Then set the check mark for "Enables" signals and switch-on the motor.
The inverter identifies the motor data after it has been switched-on. The measurement can
take several minutes. After the measurement has been completed, the inverter automatically
switches off the motor and alarm A07791 is cancelled.
● In the control panel, click on the "Give up control priority" button.
4.5.8
Additional settings
After basic commissioning, you need to carry out further settings in your inverter. Using
STARTER, you can change your inverter settings in two ways:
1.
Change the parameter values via the STARTER screens.
The screens show the most important parameters of an inverter function. If you change
the parameter values using the STARTER screens, you do not need to know the
parameter number.
2.
Change the parameter values via the STARTER expert list.
If you wish to change the parameter values using the expert list, you need to know the
parameter number.
In the section Typical commissioning scenarios (Page 55) we recommend a certain
procedure to adjust your inverter to your application in the best way possible.