Inverter with CU240B-2 and CU240E-2 Control Units
Operating Instructions, 07/2010, FW 4.3.2, A5E02299792B AA
31
Connecting
3
3.1
Procedure for installing the frequency inverter
Prerequisites for installing the inverter
Check that the following prerequisites are fulfilled before you install the inverter:
● Are the components, tools and small parts required for installation available?
● Are the ambient conditions permissible? See Technical data (Page 261).
● Have the cables and wires been routed in accordance with the applicable regulations?
See EMC-compliant connection (Page 46).
● Are the minimum distances from other equipment complied with? (Cooling sufficient?)
See Dimensions, hole drilling templates, minimum clearances, tightening torques
Installation sequence
①
Installing reactors and filters (Page 32)
②
Installing the Power Module (Page 33)
,QVWDOOLQJWKH3RZHU
0RGXOH
,QVWDOOLQJUHDFWRUV
DQGILOWHUV
,QVWDOOLQJ&RQWURO8QLW
3UHUHTXLVLWHVIRULQVWDOODWL
RQKDYHEHHQIXOILOOHG
,QVWDOODWLRQFRPSOHWHG
③
Installing Control Unit (Page 50)
You will find details on how to install the inverter in the Internet: Hardware Installation
Manual ).
You can start to commission the inverter once installation has been completed.