Commissioning
7.2 Checklists for commissioning
S-1FK7 DYA G2 synchronous motors with planetary gearbox
76
Operating Instructions, 05/2018, A5E44881183B AA
7.2
Checklists for commissioning
Note
Required checks
The lists below do not purport to be complete. It may be necessary to perform additional
checks and tests appropriate for the situation specific to the particular installation site.
Before commissioning the system, check that it is properly installed and connected.
Commission the drive system according to the Operating Instructions of the converter or
inverter being used.
Checklists for commissioning 1FK7 motors
Thoroughly familiarize yourself with the safety instructions and observe the checklists below
before starting any work.
Table 7- 1
Checklist (1) - general checks
Check
OK
Are all of the necessary components of the configured drive line-up available, correctly
dimensioned, installed and connected?
Are the manufacturer's documentation for the system components (e.g. drive system,
encoder, brake, cooling system) and the "SIMOTICS S-1FK7 G2 servomotors" Con-
figuration Manual available?
If the 1FK7 DYA G2 motor is to be operated with the SINAMICS S120 drive system:
Is the following, current SINAMICS documentation available?
•
SINAMICS S120 Commissioning Manual
•
Getting Started S120
•
S120 Function Manual
•
S120/150 List Manual
If the 1FK7 DYA G2 motor is to be operated with the SINAMICS S120 drive system:
Was the Chapter "Checklists for commissioning SINAMICS S" in the SINAMICS S120
Commissioning Manual carefully observed?
Is the motor type to be commissioned known?
(e.g. 1FK7 _ _ _ – _ _ _ _ _ – _ _ _ _)
Are the environmental conditions in the permissible range?