Mechanical mounting
5.3 Mounting/dismantling the rotor
1FE1 synchronous built-in motors
60
Hardware Installation Manual, 12/2016, 610.43000.40b
5.3.2
Preparation
Perform the following work before starting mounting:
1.
Check that the components to be joined are correct and complete.
2.
Clean the surfaces to be joined as a prerequisite for the separation and reuse of the
components later. The surfaces to be joined must be free from contamination, rust, sharp
edges, damage and machining marks.
3.
Clean the oil connection holes in accordance with the following description.
–
Remove the grub screws from the connection holes.
–
Remove oil, grease or other contaminants from the grub screws and holes (e.g. with
Loctite 7061 or 7063).
Note
Observe the manufacturer's instructions for the cleaning products used.
Ensure adequate ventilation for solvent-based products.
4.
Measure and record the radial runout of the spindle to the reference plane, see
measurement plane "R"
①
Spindle shaft
②
Position of the rotor core
③
Oiled surface (mounting without stress relief)
R
Reference plane for radial runout check
Y
Measured value (before and after mounting)
A-B Spindle shaft axis (reference axis)
Figure 5-5
Checking the radial runout