Commissioning
S7-300 Programmable Controller Hardware and Installation
A5E00105492-01
8-3
Recommended procedure - Part II: Software
Table 8-2
Recommended commissioning procedure - Part II: Software
Tasks
Remarks
Information is found in
...
•
Switch on the PG
and start SIMATIC
Manager
•
Download
the
configuration and the
program to the CPU
-
in the STEP 7
Programming Manual
Testing the I/Os
Helpful functions are here:
•
Monitoring and controlling of variables
•
Testing with program status
•
Force
•
Controlling outputs in Stop mode (PA
isolation)
Tip: If you connect switches to the inputs, you
can include the signal lines in your test.
•
in
the
STEP 7
Programming Manual
•
in
Chapter
Testing
Functions, Diagnostics
and Fault Elimination
Commission
PROFIBUS-DP or other
networks
-
in Chapter Commissioning
PROFIBUS-DP
Connect the outputs
Commissioning the outputs successively.
-
Danger
Proceed step-by-step. Do not go to the next step unless you have verified the
previous one without error/error message.
Reaction to errors
React to errors as follows:
•
Check the system with the help of the Checklist in the chapter below.
•
Check the LED displays on all modules. Notes on their significance is found in
the chapters describing the respective modules.
•
If required, remove specific modules to trace the error.
Important notes are also found ...
in Chapter Testing Functions, diagnostics and fault elimination
Summary of Contents for Simatic S7-300
Page 10: ...Contents S7 300 Programmable Controller Hardware and Installation x A5E00105492 01 ...
Page 16: ...Preface S7 300 Programmable Controller Hardware and Installation 1 6 A5E00105492 01 ...
Page 22: ...Quick Guide S7 300 Programmable Controller Hardware and Installation 2 6 A5E00105492 01 ...
Page 28: ...Product overview S7 300 Programmable Controller Hardware and Installation 3 6 A5E00105492 01 ...
Page 74: ...Configuring S7 300 Programmable Controller Hardware and Installation 4 46 A5E00105492 01 ...
Page 102: ...Wiring S7 300 Programmable Controller Hardware and Installation 6 18 A5E00105492 01 ...
Page 148: ...Commissioning S7 300 Programmable Controller Hardware and Installation 8 36 A5E00105492 01 ...
Page 236: ...Glossary S7 300 Programmable Controller Hardware and Installation 12 16 A5E00105492 01 ...