Preparing and backing up a project
7.2 Transfer
OP 73micro, TP 177micro (WinCC flexible)
Operating Instructions, 09/2007, 6AV6691-1DF01-0AB0
93
7.2.2
Starting transfer
Introduction
You can set "Transfer" mode manually on the HMI device using a configured operator
control object and during ongoing operation.
Requirements
●
The *.hmi project is opened in WinCC flexible.
●
The HMI device is connected to a configuration computer.
●
The data channel is configured on the HMI device.
●
The HMI device Loader is opened.
Procedure
Proceed as follows to initiate the transfer:
1.
Switch to "Transfer" mode on the HMI device.
2.
Proceed as follows on the configuration computer:
–
Select the "Project ▶Transfer ▶Transfer Settings" menu command in WinCC flexible.
–
Select the HMI device and define the parameters for the connection.
–
Start the download with "Transfer".
The configuration computer verifies its connection to the HMI device. If the connection is
not available or is faulty, the configuration computer outputs an alarm. If no
communication error is detected, the project is transferred to the HMI device.
Result
When the transfer is completed successfully, the data can be found on the HMI device. The
transferred project is then started automatically.
See also
Configure the data channel (Page 88)
Configure the data channel (Page 79)
Setting the operating mode (Page 90)
Data Transfer Options (Page 92)