Commissioning
8
8.1
Commissioning the ET 200 MP
Introduction
You commission the automation system in accordance with the relevant plant configuration.
The section below describes the procedure of commissioning the ET 200MP connected to
an IO controller.
Requirements for ET 200MP on PROFINET IO
Note
Performing tests
You must ensure the safety of your plant. Therefore, you must perform a complete functional
test and the necessary safety checks before the final commissioning of a plant.
Also allow for any possible foreseeable errors in the tests. In this way, you avoid
endangering persons or plants during operation.
Table 8- 1
Requirements for ET 200MP on PROFINET IO
Actions
See...
ET 200MP installed
Chapter Installation (Page 39)
ET 200MP wired
Chapter Wiring (Page 51)
ET 200MP configured
Chapter Configuring (Page 77)
Supply voltage to the I/O controller is switched on
I/O controller documentation
IO controller is in the RUN operating mode
I/O controller documentation
The operating mode transitions for the I/O controller from RUN to STOP or from STOP to
RUN can take several miliseconds, until the mode transition for the inputs and outputs of all
I/O modules for the ET 200MP station is completed. This is also true for isochronous mode.
Startup sequence for commissioning the ET 200MP
1.
Turn on the system supply voltage for the ET 200MP.
2.
Turn on the load voltage supply (PM), if necessary.
Summary of Contents for simatic ET 200MP
Page 4: ...Preface ET 200MP Distributed I O System 4 System Manual 01 2013 A5E03723484 01 ...
Page 8: ...Table of contents ET 200MP Distributed I O System 8 System Manual 01 2013 A5E03723484 01 ...
Page 118: ...Service Support ET 200MP Distributed I O System 118 System Manual 01 2013 A5E03723484 01 ...
Page 126: ...Index ET 200MP Distributed I O System 126 System Manual 01 2013 A5E03723484 01 ...